Renewable energy for Rubberatkins
Rubberatkins wind turbine is now fully operational. The project was completed on the 16th April after many weeks of construction. The project, led by Green Cat Renewables and Enercon, has taken 3 months from digging and laying foundations to the construction of the turbine and connection to the grid.